June 8th, 2020 Videos, Drone Photos & Engineer Photos
The most recent estimates for the time frame, from the meeting held on June 24, 2019, are below:
- Borings: 6/17-06/25 (1 week)
- Lab Analysis:6/26-07/17 (3 weeks)
- AE Analysis:7/17-08/14 (4 weeks)
Damage to roadway and guard rail
Bore sample drill holes – to determine composition of base material and depth of bedrock
Read the Preliminary Geotechnical Report
Learn more about soil nailing
Watch a video on soil nailing
Bald Top Update – June 8th, 2020
https://photos.google.com/share/AF1QipNpA3IFxEOxBct4DuaURGdxmIkQIw6M-mmiIwp2dq6n193jh1wnzfykjGx37ZBMYA/photo/AF1QipP14Pdd16iJMZd2mRDH7x105n_NcTbpQnp6KATA?key=bHo3U1VkWUVMRHpHOHJmZkpjLWdYekVjblVReEFn https://photos.google.com/share/AF1QipNpA3IFxEOxBct4DuaURGdxmIkQIw6M-mmiIwp2dq6n193jh1wnzfykjGx37ZBMYA/photo/AF1QipOSwvK1xC4Z-OO_sfzRRuP6HL3s2tyxXM8Jwyib?key=bHo3U1VkWUVMRHpHOHJmZkpjLWdYekVjblVReEFn
Bald Top Update:
Preliminary readings from inclinometers on Bald Top road show a cumulative movement of 3/100th of an inch with depths varying greater than 20 feet. Because this information is so preliminary it is as yet inconclusive, the total of the readings planned being scheduled for three months. The Township is incurring costs in excess of $6,000 per month for the monitoring, … Read More
Bald Top Update from the Public Meeting held Monday, June 24, 2019
The most recent estimates for the time frame, from the meeting held on June 24, 2019, are below: ▪ Borings: 6/17-06/25 (1 week) ▪ Lab Analysis:6/26-07/17 (3 weeks) ▪ AE Analysis:7/17-08/14 (4 weeks) Once completed, work will begin on designing the method for the permanent repair. It will be the middle to the end of August before we can bid … Read More
Bald Top Road Safety Issue
It’s been reported that motorists are driving around the barricades on Bald Top Road. The barricades were set up for your safety. Anyone caught driving around them will be cited.