Bald Top Update from the Public Meeting held Monday, June 24, 2019

Carolyn DraganoBald Top Road, News

The most recent estimates for the time frame, from the meeting held on June 24, 2019, are below:

▪ Borings: 6/17-06/25 (1 week)
▪ Lab Analysis:6/26-07/17 (3 weeks)
▪ AE Analysis:7/17-08/14 (4 weeks)

Once completed, work will begin on designing the method for the permanent repair. It will be the middle to the end of August before we can bid the work.